Weymouth Harbour Walls Update

15 October 2019

Good progress is being made with piling commencing yesterday (14 October), however due to weather conditions and unknown ground conditions which can both delay piling, the team are remaining cautious.

An entire length of the waling beam will be exposed this week which is a key structural element of the existing wall. Its condition will be checked to make sure it can support the new stronger steel sheet pile wall. The piling will be closely monitored using live data from the noise, vibration and dust monitoring stations to do this.

Visit dorsetcouncil.gov.uk/weyharbourworks or follow #weyharbourworks for all current information.