Site Works Update

27 March 2024

Ducting work has continued in compounds A and B, with still more programmed for compound A.

Palisade fencing has been erected at compound C – the area near the top of the Pavilion car park - to prevent casual access to the commercial area.

The base for the high voltage kiosk has been laid, along with mains water supply and Aco drains plus the very first building for the new fishermen facilities, the fish bait store is now in place.

You will also have noticed lots of re-surfacing taking place for the new public walkway where the departure lounge stood previously.

Over the next few weeks include more ducting and drainage, the new fence line will be installed around compounds B&C as well as work for the fuel tank area commencing with tanker slab, separator slab and ACO drains being installed.